DESIGN OF PIT X BASED ON PRODUCTION TARGETS USING MINE SCHEDULING CONCEPT AT PT Y

https://doi.org/10.56139/intan.v8i2.349

Authors

  • Ardhan Ismail Program Studi Teknik Pertambangan, Universitas Mulawarman
  • Mochamad Gaharu Dida Devedo Program Studi Teknik Sipil, Universitas Mulawarman
  • Albertus Juvensius Pontus Program Studi Teknik Pertambangan, Universitas Mulawarman
  • Anita oktoviana L.P.G.M. Thomas Program Studi Teknik Pertambangan, Universitas Teknologi Sumbawa

Abstract

Pit design in surface mining requires a systematic approach that considers operational capacity and efficiency to ensure optimal production target achievement. In the actual condition of the second quarter of 2025, pit X design at PT Y was carried out manually using a trial-and-error method. This method was time-consuming and less flexible to parameter changes, and caused significant deviations from production targets, with overburden reaching 110%, coal only 89%, and stripping ratio increasing to 4.19 from the target of 3.39. This study aims to develop pit design based on Mine Scheduling Concept using SPRY Scheduler software to improve operational effectiveness and efficiency. An applied quantitative method was implemented by integrating reserve data from Minescape, heavy equipment parameters including availability, utilisation, and hourly rate, as well as a mining calendar aligned with operational conditions in the third quarter of 2025. The results show that the generated pit design achieves production targets with very high accuracy: overburden of 4,093,991 Bcm with a deviation of -0.02%, coal of 1,206,663 MT with a deviation of 0.00%, and a stripping ratio of 3.39 as targeted. The application of SPRY Scheduler produces measurable, accurate, and adaptive pit designs without trial-and-error processes, supporting efficient and sustainable mine planning.

Downloads

Download data is not yet available.

References

. Ministry of Energy and Mineral Republic of Indonesia. 2024. “handbook-of-energy-and-economic-statistics-of-indonesia-2024, ”Available: https://www.esdm.go.id/en/ publication/handbook-of-energy-economic-statistics-of-indonesia-heesi. Accessed: Oct. 18, 2025.

. E. Hay, M. Nehring, P. Knights, and M. S. Kizil. 2019. “Determining the optimal orientation of ultimate pits for mines using fully mobile in-pit crushing and conveying systems,” The Journal of the Southern African Institute of Mining and Metallurgy, vol. 119, doi: 10.17159/2411.

. M. Osanloo, J. Gholamnejad, and B. Karimi. 2008. “Long-term open pit mine production planning: A review of models and algorithms,” doi: 10.1080/17480930601118947.

. N. Morales, P. Nancel-Penard, and N. Espejo. 2023. “Development and analysis of a methodology to generate operational open-pit mine ramp designs automatically,” Optimization and Engineering, vol. 24, no. 2, pp. 711–741, doi: 10.1007/s11081-021-09702-3.

. M. A. O. Talayuk, D. N. Tanggara, I. P. Putrawiyanta, N. Novalisae, and Y. D. Inso, 2025. “Technical Design of Pit B Mining PT Indo Muro Kencana Murung Raya Regency, Central Kalimantan Province,” G-Tech: Jurnal Teknologi Terapan, vol. 9, no. 4, pp. 1782–1789, doi: 10.70609/g-tech.v9i4.7790.

. D. Yulhendra, F. Sandrio, and A. Octova. 2023. “Development Mine Scheduling Concept in Making Pit Design,” MOTIVECTION : Journal of Mechanical, Electrical and Industrial Engineering, vol. 5, no. 2, pp. 269–282, doi: 10.46574/motivection.v5i2.208.

. A. M. Newman, E. Rubio, R. Caro, A. Weintraub, and K. Eurek. 2010. “A review of operations research in mine planning,” Interfaces (Providence), vol. 40, no. 3, pp. 222–245. doi: 10.1287/inte.1090.0492.

. K. Tabang, K. Kutai Kartanegara, P. Kalimantan Timur Hendra Sani, and T. Tappang. 2025. “Rancangan Desain Pit Short Term Di Pit Panel II PT. Karunia Armada Indonesia Jobsite PT. Indonesia Pratama,” Jurnal Teknik AMATA, vol. 6, no. 1. 9.

. M. Blom, A. R. Pearce, and P. J. Stuckey. 2017. “Short-term planning for open pit mines: a review,” Int J Min Reclam Environ, vol. 33, no. 5, pp. 318–339, doi: 10.1080/17480930.2018. 1448248.10.

. E. Moreno, M. Rezakhah, A. Newman, and F. Ferreira, 2017. “Linear models for stockpiling in open-pit mine production scheduling problems,” Eur J Oper Res, vol. 260, no. 1, pp. 212–221, doi: 10.1016/j.ejor.2016.12.014.

Published

2025-11-15

How to Cite

Ismail, A., Mochamad Gaharu Dida Devedo, Pontus, A. J., & Thomas , A. oktoviana L. . (2025). DESIGN OF PIT X BASED ON PRODUCTION TARGETS USING MINE SCHEDULING CONCEPT AT PT Y. INTAN Jurnal Penelitian Tambang, 8(2), 70–80. https://doi.org/10.56139/intan.v8i2.349