STUDY OF CALCULATION OF RUNAWAY DISCHARGE INTO EFO SETTLING POND AT PT GAG NIKEL, SOUTHWEST PAPUA PROVINCE

KAJIAN PERHITUNGAN DEBIT LIMPASAN YANG MASUK PADA SETTLING POND EFO DI PT GAG NIKEL PROVINSI PAPUA BARAT DAYA

https://doi.org/10.56139/intan.v8i1.294

Authors

  • Felice Deglardini Wopari Teknik Pertambangan dan Geologi Universitas Cenderawasih
  • Fandi Arapenta Ginting Pertambangan Universitas Cenderawasih
  • Fajrianti Nur Hajijah
  • Lia Medy Tandy

Keywords:

catchment area, discharge, settling pond, runoff, volume

Abstract

Settling Pond EFO is one of the mine water management facilities managed by PT Gag Nikel, functioning as a water reservoir and sedimentation deposition site. This study evaluates the suitability of the Settling Pond EFO capacity to the incoming runoff discharge, especially in high rainfall conditions. Based on the analysis results, the runoff discharge entering the Settling Pond EFO reached 0.42 m³/second, with a catchment area of ​​0.188 km² and a rainfall intensity of 10.54 mm/hour. The evaluation showed three main findings: (1) There is a change in volume between the initial design of the pond and the actual conditions due to long-term use; (2) The Settling Pond EFO has the potential to be full if it rains for 11 hours; and (3) The Settling Pond capacity has not been optimally utilized, with the remaining unfilled volume of 1,636.90 m³. These results indicate the importance of optimizing the capacity and management of the Settling Pond to overcome the risk of excess runoff.

Downloads

Download data is not yet available.

References

Adnyano, A.I. & Bagaskoro, M., 2020. Kajian teknis dewatering system tambang pada pertambangan batubara. Vol. 8(1), pp.28–33.

Arindry, A.P., Syahrudin & Herlambang, Y., 2020. Evaluasi kapasitas kolam pengendapan unit pencucian bauksit pada washing plant Cabing Km 23 PT Dinamika Sejahtera Mandiri site Teraju Kabupaten Sanggau Kalimantan Barat. JeLAST: Jurnal PWK, Laut, Sipil, Tambang, 7(1).

Astarini, A. & Adriat, R., 2022. Studi perbandingan metode penentuan intensitas curah hujan berdasarkan karakteristik curah hujan Kalimantan Barat. Prisma Fisika, 10(1), pp.109–114.

Asdak, C., 2002. Hutan dan perilaku aliran air: klarifikasi keberadaan hutan dan pengaruhnya terhadap banjir dan kekurangan air. Jurnal Manusia dan Lingkungan, 9(1), pp.40–49.

Asdak, C., 2014. Kajian lingkungan hidup strategis: jalan menuju pembangunan berkelanjutan. Yogyakarta: Gadjah Mada University Press.

Cahyadi, T.A. et al., 2020. Evaluasi saluran terbuka dengan menggunakan distribusi Gumbel dan model Thomas Fiering. Kurvatek, 5(1), pp.29–36.

Firdaus et al., 2023. Evaluasi kinerja kolam pengendap lumpur (KPL) batubara di stockpile PT Bukit Asam Tbk unit Pelabuhan Tarahan. Jurnal Hutan Tropis, 11(1), pp.84–91.

Gautama, R.S., 2019. Sistem penyaliran tambang. Bandung: Institut Teknologi Bandung.

Haeruman, H., 1944. Pengelolaan daerah aliran sungai. Lokakarya Pengelolaan DAS Terpadu, Cisarua, Bogor.

Kurnia, D., Har, R. & Prabowo, H., 2018. Evaluasi kondisi aktual dan perencanaan sistem penyaliran tambang emas di Pit Durian, Site Bakan PT J Resources Bolaang Mongondow, Kecamatan Lolayan, Kotamobagu, Sulawesi Utara. Jurnal Bina Tambang, 3(1), pp.1–7.

Michael, P.E.T.E.R., Superfesky, M.I.C.H.A.E.L. & Uranoswki, L., 2010. Challenges of applying geomorphic and stream reclamation methodologies to mountaintop mining and excess spoil fill construction in steep slope topography (e.g. Central Appalachia). In: Proceedings of the Joint Conference of the 27th Annual Meetings of the American Society of Mining and Reclamation, 12th Annual Pennsylvania Abandoned Mine Reclamation Conference, and 4th Annual Appalachian Regional Reforestation Initiative Mined Land Reforestation Conference. Lexington: ASMR, pp.610–634.

Parhusip, M., Ernawati, R. & Cahyadi, T.A., 2021. Evaluasi settling pond pada area Run of Mine (ROM). Jurnal Inovasi Pertambangan dan Lingkungan (JIPL), 1(1), pp.1–9.

Permanadewi, S., Wahyudiono, J. & Tampubolon, A., 2017. Cebakan nikel laterit di Pulau Gag, Kabupaten Raja Ampat, Provinsi Papua Barat. Buletin Sumber Daya Geologi, 12(1), pp.55–70. Setianingrum, N. & Yulianti, R., 2020. Evaluasi kolam pengendapan lumpur (SP 10) terhadap debit air pompa yang masuk (Studi kasus: PT Trisensa Mineral Utama, Tani Aman, Kalimantan Timur). Indonesian Mining and Energy Journal, 3(2), pp.59–64.

Silisa, L.J., Rande, S.A. & Misdayanta, P., 2022. Rencana teknis pemeliharaan kolam pengendapan di area EFO PT Gag Nikel Provinsi Papua Barat. Mining Insight, 3(1), pp.11–20.

Syajruddin, Musa, R. & Ashad, H., 2022. Kajian debit limpasan akibat intensitas curah hujan terhadap variasi kepadatan dan kemiringan lahan. Jurnal Konstruksi: Teknik, Infrastruktur dan Sains, pp.41–50.

Towansiba, N. & Pangkung, Y.G., 2020. Rancangan settling pond terhadap laju endapan sedimen pada area Arafah dan waste dump pada front penambangan PT Gag Nikel, Kab. Raja Ampat, Provinsi Papua Barat. Intan: Jurnal Penelitian Tambang, 3(1), pp.35–39.

Triatmodjo, B., 2008. Hidrologi terapan. Yogyakarta: Beta Offset.

Utamakno, L., Budiarto & Tinungki, P.S., 2020. Rancangan pemodelan settling pond pada daerah Imkasu di PT Gag Nikel, Pulau Gag, Kabupaten Raja Ampat, Papua Barat. Prosiding SEMITAN II, 2(1), pp.95–101.

Published

2025-06-13

How to Cite

Wopari, F. D., Ginting, F. A. ., Hajijah, F. N., & Tandy, L. M. (2025). STUDY OF CALCULATION OF RUNAWAY DISCHARGE INTO EFO SETTLING POND AT PT GAG NIKEL, SOUTHWEST PAPUA PROVINCE: KAJIAN PERHITUNGAN DEBIT LIMPASAN YANG MASUK PADA SETTLING POND EFO DI PT GAG NIKEL PROVINSI PAPUA BARAT DAYA. INTAN Jurnal Penelitian Tambang, 8(1). https://doi.org/10.56139/intan.v8i1.294